Requirement Overview

Cleaning completion is not the same as production readiness.

Before food production begins, facilities should have a structured method for determining whether processing areas, equipment, utensils, food-contact surfaces, and supporting conditions are ready for operation.

Cleaning may have been completed, but cleaning completion alone does not necessarily demonstrate production readiness.

Equipment may have been improperly reassembled. Food residues may remain in difficult-to-clean locations. Maintenance debris, standing water, condensation, damaged components, chemical residues, allergen residues, or foreign materials may still be present.

A pre-operational inspection provides a formal checkpoint between sanitation or maintenance activities and the start of food production.

Pre-operational conditions may include evaluation of:

  • Food-contact surfaces
  • Processing equipment
  • Utensils
  • Floors and drains
  • Walls and overhead structures
  • Condensation
  • Cleaning effectiveness
  • Chemical residues
  • Allergen residues
  • Foreign materials
  • Equipment integrity
  • Maintenance conditions
  • Glass and brittle plastic
  • Pest activity
  • Employee hygiene stations
  • Production-area readiness

Our HACCP Pre-Operational Inspection Program Development Service helps food businesses establish documented procedures for inspecting, documenting, correcting, verifying, and releasing processing areas before production begins.

CIG evaluates facility conditions, sanitation programs, equipment, HACCP risks, production activities, and existing pre-operational practices to develop a practical inspection and release framework appropriate to the operation.


Why Pre-Operational Inspections Matter

The Best Time to Identify a Food Safety Condition Is Before Product Is Exposed

Once production begins, an unacceptable condition can become a product-control issue.

A small amount of residual food, a loose equipment component, condensation above an exposed product area, an incorrectly assembled machine, or an unclean food-contact surface can potentially affect significant quantities of product if not identified before startup.

Weak pre-operational controls may contribute to:

  • Microbiological contamination
  • Allergen cross-contact
  • Foreign material contamination
  • Chemical contamination
  • Environmental contamination
  • Equipment-related contamination
  • Product holds
  • Production delays
  • Recleaning during operations
  • Repeated sanitation failures
  • Audit findings
  • Customer complaints

A structured pre-operational inspection program helps verify that identified food safety conditions have been addressed before production is authorized to begin.

Effective pre-operational controls can help organizations:

  • Verify sanitation effectiveness
  • Inspect food-contact surfaces
  • Identify residual product or soil
  • Identify allergen concerns
  • Detect foreign material risks
  • Verify equipment condition
  • Identify maintenance-related issues
  • Check condensation and environmental conditions
  • Document corrective actions
  • Establish formal production-release authority

Our HACCP Pre-Operational Inspection Services

40 services from inspection scope and criteria through production release.

Pre-Operational Program Gap Assessment

CIG evaluates existing pre-operational practices to identify opportunities for strengthening inspection, documentation, corrective action, and release controls.

Assessment May Include

  • Existing pre-op procedures
  • Inspection responsibilities
  • Inspection timing
  • Inspection scope
  • Food-contact surface checks
  • Equipment inspection
  • Sanitation verification
  • Allergen controls
  • Maintenance conditions
  • Foreign material controls
  • Environmental conditions
  • Corrective action procedures
  • Production release
  • Records and verification

The assessment helps determine whether the existing system provides an effective checkpoint before production startup.

Pre-Operational Inspection Scope Development

CIG helps define what should be included within the facility's pre-operational inspection program.

Scope May Include

  • Production rooms
  • Processing lines
  • Food-contact equipment
  • Utensils
  • Ingredient-handling areas
  • Packaging areas
  • Ready-to-eat areas
  • High-care or high-hygiene areas
  • Raw-processing areas
  • Storage areas
  • Employee hygiene stations
  • Sanitation equipment
  • Maintenance-affected areas

The scope can be tailored according to product exposure, process risk, and facility design.

Pre-Operational Inspection Procedure Development

CIG can develop a standardized procedure governing how inspections are performed before production.

Procedures May Define

  • Inspection timing
  • Inspection sequence
  • Responsible personnel
  • Required inspection areas
  • Acceptance criteria
  • Inspection tools
  • Documentation requirements
  • Failed-inspection response
  • Reinspection requirements
  • Production-release authority
  • Verification activities

Food-Contact Surface Inspection

Food-contact surfaces should be visually clean and in an appropriate condition before production.

CIG can establish inspection criteria for food-contact equipment and surfaces.

Inspection May Include

  • Residual food material
  • Soil or buildup
  • Grease
  • Chemical residues
  • Water accumulation
  • Biofilm indicators
  • Foreign material
  • Surface damage
  • Corrosion
  • Cracks
  • Equipment condition
  • Sanitation status

Difficult-to-Clean & Harborage Area Inspection

Certain equipment areas may require focused inspection because residues or moisture can accumulate in locations that are difficult to access.

CIG can help identify high-risk inspection points.

Areas May Include

  • Equipment joints
  • Gaskets
  • Seals
  • Hollow areas
  • Conveyor interfaces
  • Rollers
  • Belts
  • Guards
  • Undersides of equipment
  • Product transfer points
  • Dead ends
  • Drain-adjacent equipment
  • Framework and supports

Equipment Assembly & Readiness Inspection

Equipment may be clean but still unsuitable for production if components are missing, incorrectly installed, or improperly assembled.

CIG can establish equipment-readiness criteria.

Inspection May Include

  • Correct assembly
  • Guards and covers
  • Gaskets and seals
  • Screens and filters
  • Fasteners
  • Belts
  • Product-contact components
  • Drain plugs
  • Equipment settings
  • Missing parts
  • Loose components
  • General operational condition

Sanitation Completion Verification

CIG helps establish a formal link between sanitation completion and pre-operational inspection.

Verification May Include

  • Sanitation task completion
  • Cleaning records
  • Required chemicals used
  • Equipment disassembly
  • Cleaning completion
  • Sanitizer application
  • Rinse requirements
  • Chemical concentration records
  • Sanitation deficiencies
  • Corrective actions

Production release should occur only after applicable sanitation and inspection requirements have been satisfied.

Visual Cleanliness Standards Development

Terms such as “clean” can be interpreted differently by different employees.

CIG can help establish practical visual acceptance criteria.

Criteria May Address

  • Visible food residues
  • Product buildup
  • Grease
  • Standing water
  • Dust
  • Debris
  • Chemical residues
  • Foreign materials
  • Staining versus removable soil
  • Equipment-specific expectations

Clear standards can improve consistency among inspectors and sanitation personnel.

ATP Verification Integration

Where ATP testing is used as part of sanitation verification, CIG can integrate it into the pre-operational program.

Program Elements May Include

  • Sampling locations
  • Sampling frequency
  • Testing responsibility
  • Acceptance criteria
  • Failed-result response
  • Recleaning requirements
  • Retesting
  • Production-release criteria
  • Trending
  • Documentation

ATP results should be interpreted according to the facility's validated or established sanitation verification approach and equipment used.

Microbiological Verification Integration

Certain facilities may use microbiological surface testing to verify sanitation or environmental conditions.

CIG can help integrate applicable microbiological verification activities with the pre-operational program.

Integration May Include

  • Sampling locations
  • Sampling schedules
  • Food-contact surfaces
  • Non-food-contact surfaces
  • Result review
  • Escalation criteria
  • Corrective actions
  • Resampling
  • Trend analysis
  • Environmental monitoring coordination

Allergen Pre-Operational Verification

Facilities producing products with different allergen profiles may require additional verification following allergen changeovers.

CIG can establish allergen-focused pre-operational inspection requirements.

Controls May Include

  • Production schedule review
  • Previous product identification
  • Allergen profile review
  • Changeover sanitation verification
  • Equipment inspection
  • Utensil inspection
  • Allergen test results where applicable
  • Rework removal
  • Label and packaging verification
  • Production release

Foreign Material Pre-Operational Inspection

Foreign materials introduced during sanitation, maintenance, or overnight activities may remain in production areas.

CIG can incorporate foreign material checks into pre-operational inspections.

Inspection May Include

  • Loose hardware
  • Metal fragments
  • Broken plastic
  • Glass
  • Wood
  • Wire
  • Maintenance debris
  • Cleaning-tool fragments
  • Packaging debris
  • Personal items
  • Missing equipment components

Glass & Brittle Plastic Inspection Integration

Facilities maintaining glass and brittle plastic programs can incorporate applicable checks into pre-operational inspections.

Inspection May Include

  • Lighting covers
  • Equipment displays
  • Plastic guards
  • Windows
  • Instrument covers
  • Brittle plastic components
  • Breakage evidence
  • Condition changes
  • Required corrective actions

Maintenance-Related Pre-Operational Inspection

Equipment that has undergone maintenance may require enhanced inspection before returning to production.

CIG can establish specific post-maintenance pre-operational requirements.

Inspection May Include

  • Tool removal
  • Parts reconciliation
  • Loose hardware
  • Maintenance debris
  • Lubricants
  • Temporary repairs
  • Equipment assembly
  • Food-contact surface condition
  • Cleaning and sanitation
  • Calibration or verification
  • Equipment functionality

Temporary Repair Inspection

Temporary repairs should be monitored to ensure they remain intact and do not create contamination risks.

CIG can integrate temporary repair review into pre-operational inspections.

Review May Include

  • Repair condition
  • Repair material
  • Product exposure
  • Cleanability
  • Loose components
  • Foreign material risk
  • Repair due date
  • Escalation status

Condensation & Overhead Condition Inspection

Condensation and overhead contamination can create risks when located above exposed product or food-contact surfaces.

CIG can establish inspection requirements.

Inspection May Include

  • Condensation
  • Dripping water
  • Pipes
  • Ceilings
  • Overhead structures
  • HVAC components
  • Dust accumulation
  • Flaking material
  • Corrosion
  • Insulation condition
  • Lighting fixtures

Floors, Walls & Drain Inspection

Pre-operational inspections can extend beyond equipment to the surrounding production environment.

CIG can establish criteria for environmental conditions.

Inspection May Include

  • Standing water
  • Drain cleanliness
  • Drain backups
  • Floor condition
  • Wall condition
  • Residual debris
  • Cleaning chemical residues
  • Pest evidence
  • Waste removal
  • Unusual odors
  • Splash risks

Hygienic Zone Readiness Inspection

Facilities with defined hygienic zones may require zone-specific startup checks.

CIG can integrate hygienic zoning requirements into the pre-operational program.

Inspection May Include

  • Zone barriers
  • Controlled access
  • Hygiene stations
  • Footwear controls
  • Dedicated tools
  • Employee clothing
  • Equipment segregation
  • Cleaning-tool segregation
  • Material staging
  • Environmental conditions

Ready-to-Eat & Post-Process Area Inspection

Areas handling exposed ready-to-eat or post-process products may require enhanced pre-operational controls.

CIG can establish additional inspection requirements based on facility risk.

Review May Include

  • Food-contact surfaces
  • Environmental conditions
  • Employee hygiene stations
  • Equipment sanitation
  • Condensation
  • Traffic controls
  • Utensil storage
  • Product-contact packaging
  • Zone barriers
  • Maintenance activity
  • Environmental monitoring considerations

Cleaning Tool & Sanitation Equipment Inspection

Cleaning tools themselves can become contamination sources if damaged, dirty, or stored incorrectly.

CIG can incorporate sanitation-tool checks.

Inspection May Include

  • Brushes
  • Brooms
  • Squeegees
  • Scrapers
  • Hoses
  • Foamers
  • Buckets
  • Cleaning carts
  • Tool condition
  • Tool segregation
  • Storage practices

Chemical Control Pre-Operational Inspection

Cleaning and maintenance chemicals should not remain inappropriately positioned or present on food-contact surfaces when production begins.

CIG can establish chemical-related checks.

Inspection May Include

  • Chemical removal
  • Correct storage
  • Chemical labeling
  • Residual cleaning chemicals
  • Lubricants
  • Maintenance chemicals
  • Unidentified containers
  • Chemical dispensing equipment
  • Required rinse completion

Pest Activity Pre-Operational Observation

Evidence of pest activity identified before production should be appropriately evaluated.

CIG can incorporate pest observations into pre-operational inspections.

Observations May Include

  • Insects
  • Rodent evidence
  • Droppings
  • Gnawing
  • Nesting materials
  • Dead pests
  • Entry-point concerns
  • Damaged pest-control devices
  • Product contamination evidence

Findings can be escalated through the facility's pest management and corrective action programs.

Employee Hygiene Station Readiness

Employee hygiene controls should be functional before production begins.

CIG can establish startup inspection requirements for applicable hygiene stations.

Inspection May Include

  • Handwashing stations
  • Soap availability
  • Hand drying
  • Sanitizer availability
  • Footwear sanitation systems
  • Gowning supplies
  • Hair restraints
  • Glove supplies
  • Waste containers
  • Station cleanliness

Pre-Operational Inspection Frequency

CIG helps determine when inspections should occur based on the operation.

Inspections May Be Required

  • Before daily production
  • Before each shift
  • Following sanitation
  • Following allergen changeovers
  • Following maintenance
  • After extended shutdowns
  • Following construction
  • Following contamination events
  • Before restarting held equipment
  • When production zones change status

Pre-Operational Inspector Responsibility & Authority

Personnel performing inspections should understand what they are authorized to accept, reject, or escalate.

CIG can establish responsibility and authority requirements.

Roles May Include

  • Sanitation personnel
  • Quality assurance
  • Food safety personnel
  • Production supervisors
  • Maintenance personnel
  • PCQI or HACCP personnel where applicable
  • Management

Responsibilities can distinguish between cleaning completion, inspection, corrective action, verification, and final release.

Failed Pre-Operational Inspection Response

When an unacceptable condition is identified, production should not proceed in the affected area until the condition has been appropriately addressed.

CIG can establish a structured failure-response procedure.

Response May Include

  • Document the finding
  • Identify affected equipment or area
  • Prevent production startup
  • Reclean or sanitize
  • Remove foreign material
  • Correct maintenance conditions
  • Repair equipment
  • Address allergen concerns
  • Reinspect the area
  • Perform additional verification where appropriate
  • Document corrective action
  • Authorize release

Reinspection & Verification

Correcting a deficiency does not automatically close the finding.

CIG can establish reinspection requirements to verify that the corrective action was effective.

Reinspection May Include

  • Visual inspection
  • ATP testing where applicable
  • Allergen testing where applicable
  • Equipment integrity review
  • Sanitation verification
  • Maintenance verification
  • Environmental condition review
  • Documentation of acceptance

Production Release Authorization

A structured pre-operational program should clearly identify who may authorize production startup.

CIG can establish formal release procedures.

Release May Require

  • Inspection completion
  • Acceptable inspection findings
  • Corrective action closure
  • Reinspection completion
  • Required test results
  • Maintenance clearance
  • Sanitation clearance
  • Allergen clearance
  • Inspector approval
  • Release date and time

Conditional Release & Escalation Controls

Certain observations may require management or food safety review before production can proceed.

CIG can establish escalation criteria.

Escalation May Address

  • Repeated sanitation failures
  • Unresolved maintenance issues
  • Environmental concerns
  • Potential pathogen findings
  • Allergen concerns
  • Significant foreign material risks
  • Utility failures
  • Structural deficiencies
  • Uncertain equipment condition

Pre-Operational Inspection Checklist Development

CIG can develop facility-specific inspection checklists aligned with the operation.

Checklist Sections May Include

  • Room condition
  • Food-contact surfaces
  • Equipment assembly
  • Sanitation status
  • Allergen controls
  • Foreign material controls
  • Glass and brittle plastic
  • Maintenance conditions
  • Temporary repairs
  • Condensation
  • Floors and drains
  • Hygiene stations
  • Pest observations
  • Cleaning tools
  • Chemical controls
  • Production release

Area-Specific Pre-Operational Checklists

Large or complex facilities may benefit from separate checklists for different processing areas.

CIG can develop area-specific inspection tools for

  • Receiving areas
  • Raw processing
  • Cooking areas
  • Cooling areas
  • Ready-to-eat areas
  • Packaging rooms
  • Allergen-controlled areas
  • High-care areas
  • Warehouses
  • Cold rooms
  • Sanitation areas

Pre-Operational Deficiency Classification

Not every observation has the same food safety significance.

CIG can establish a framework for classifying inspection findings.

Classifications May Consider

  • Food-contact versus non-food-contact
  • Product exposure
  • Biological hazard potential
  • Allergen potential
  • Chemical hazard potential
  • Physical hazard potential
  • Immediate correction requirements
  • Production-stop criteria
  • Escalation requirements

Repeated Deficiency & Root Cause Analysis

Recurring pre-operational failures may indicate problems beyond individual cleaning errors.

CIG can establish criteria for escalation and root cause analysis.

Investigation May Consider

  • Sanitation methods
  • Cleaning frequencies
  • Equipment design
  • Employee training
  • Chemical selection
  • Chemical concentration
  • Maintenance conditions
  • Equipment accessibility
  • Production practices
  • Responsibility assignments
  • Verification effectiveness

Pre-Operational Corrective Action Management

CIG helps establish corrective action procedures for deficiencies identified during inspections.

Corrective Actions May Include

  • Recleaning
  • Resanitizing
  • Equipment repair
  • Component replacement
  • Condensation correction
  • Drain cleaning
  • Foreign material removal
  • Chemical removal
  • Allergen recleaning
  • Employee retraining
  • Procedure revision
  • Preventive maintenance
  • Sanitation program modification

Pre-Operational Inspection Trending

Inspection findings can provide valuable information about sanitation and facility performance.

CIG can establish methods for trending pre-operational data.

Trending May Include

  • Failure frequency
  • Equipment
  • Production line
  • Facility area
  • Deficiency type
  • Food-contact surface failures
  • ATP failures
  • Allergen failures
  • Maintenance findings
  • Condensation findings
  • Repeat deficiencies
  • Corrective actions

Trend analysis can help identify recurring conditions before they develop into more significant food safety issues.

Pre-Operational Performance Indicators

CIG can help establish measurable indicators for evaluating program effectiveness.

Indicators May Include

  • First-pass inspection rate
  • Recleaning frequency
  • Repeat failure rate
  • ATP failure rate
  • Allergen verification failure rate
  • Maintenance-related findings
  • Delayed startup events
  • Recurring equipment deficiencies
  • Corrective action closure rate

Pre-Operational Record Development

CIG can develop standardized documentation supporting the inspection and release process.

Records May Include

  • Pre-operational inspection checklist
  • Equipment-specific inspection form
  • Sanitation verification record
  • ATP verification log
  • Allergen verification record
  • Maintenance clearance form
  • Corrective action record
  • Reinspection record
  • Production release authorization
  • Deficiency trend report
  • Pre-operational verification record

Pre-Operational Program Verification

Organizations should periodically verify that inspections are performed consistently and that findings are appropriately addressed.

CIG can establish verification activities.

Verification May Include

  • Checklist review
  • Direct observation of inspections
  • Inspector competency review
  • Corrective action review
  • Reinspection record review
  • Release authorization review
  • ATP or testing trend review
  • Repeat deficiency analysis
  • Internal audits
  • Management review

Inspector Training & Competency Support

Pre-operational inspections are more effective when inspectors understand what they are looking for and why it matters.

CIG can help establish training content and competency expectations.

Training May Address

  • Inspection purpose
  • Food safety hazards
  • Visual inspection techniques
  • Food-contact surfaces
  • Equipment condition
  • Allergen risks
  • Foreign material risks
  • Maintenance findings
  • Condensation
  • Documentation
  • Corrective actions
  • Release authority

HACCP Integration Review

Pre-operational inspection should support the broader HACCP and prerequisite program structure.

CIG evaluates how startup inspections interact with existing food safety controls.

Integration May Include

  • Hazard analysis
  • Sanitation programs
  • Allergen management
  • Environmental monitoring
  • Hygienic zoning
  • Preventive maintenance
  • Foreign material controls
  • Calibration
  • Pest management
  • Product hold and release
  • Corrective actions
  • Verification activities
  • HACCP reassessment

Pre-Operational Inspection Program Deliverables

What you receive at the end of the engagement.

Depending on the selected scope, deliverables may include:

  • Pre-operational program gap assessment
  • Inspection scope and applicability matrix
  • Pre-operational inspection procedure
  • Food-contact surface inspection criteria
  • Difficult-to-clean area inspection criteria
  • Equipment readiness requirements
  • Sanitation completion verification requirements
  • Visual cleanliness standards
  • ATP verification integration
  • Microbiological verification integration
  • Allergen pre-op verification requirements
  • Foreign material inspection requirements
  • Glass and brittle plastic checks
  • Post-maintenance inspection requirements
  • Temporary repair inspection requirements
  • Condensation and overhead inspection criteria
  • Floor and drain inspection criteria
  • Hygienic zone readiness requirements
  • RTE and post-process area requirements
  • Cleaning-tool inspection requirements
  • Chemical-control checks
  • Pest observation requirements
  • Hygiene station readiness checks
  • Inspection frequency matrix
  • Inspector responsibility matrix
  • Failed-inspection response procedure
  • Reinspection procedure
  • Production release procedure
  • Escalation criteria
  • Facility-specific inspection checklists
  • Area-specific checklists
  • Deficiency classification framework
  • Corrective action procedure
  • Root cause escalation criteria
  • Trend-analysis framework
  • Performance indicators
  • Supporting forms and records
  • Inspector training recommendations
  • HACCP integration recommendations
  • Implementation roadmap

Who This Service Is Ideal For

Built for operations at every stage of HACCP maturity.

Our HACCP Pre-Operational Inspection Program Development Service is designed for:

  • Food manufacturers
  • Food processors
  • Meat and poultry establishments
  • Seafood processors
  • Juice processors
  • Dairy and cheese facilities
  • Bakery and confectionery operations
  • Ready-to-eat food manufacturers
  • Frozen food manufacturers
  • Beverage manufacturers
  • Ingredient manufacturers
  • Fresh produce packing facilities
  • Commercial kitchens and commissaries
  • Private-label manufacturers
  • Co-manufacturers and contract processors
  • Facilities with allergen changeovers
  • Facilities operating high-care or high-hygiene areas
  • Facilities experiencing recurring sanitation deficiencies
  • Organizations addressing pre-op audit findings
  • FDA and USDA-regulated food operations
  • SQF, BRCGS, FSSC 22000, and other GFSI-certified organizations

Why Choose Consultare Inc. Group (CIG)

Inspect Before Production. Correct Before Exposure. Document Before Release.

CIG helps organizations transform pre-operational inspection from a basic visual walkthrough into a structured food safety verification and production-release process.

Facility-Specific Inspection Development

Pre-operational requirements are developed around the actual equipment, products, hazards, hygienic zones, sanitation methods, and production activities within the facility.

HACCP & Sanitation Integration

CIG connects pre-operational inspections with sanitation, allergen management, preventive maintenance, foreign material control, environmental monitoring, and HACCP verification.

Clear Acceptance & Release Criteria

We help establish what inspectors should evaluate, what constitutes an unacceptable condition, what corrective action is required, and who has authority to release the area for production.

Corrective Action & Reinspection Controls

Deficiencies are not considered resolved simply because cleaning or repair has occurred. The program can require documented correction and reinspection before release.

Trend-Based Program Improvement

Pre-operational records can be structured to identify recurring equipment, sanitation, environmental, or maintenance problems and support longer-term corrective actions.

Practical Documentation

CIG can develop inspection checklists, deficiency records, corrective action forms, reinspection records, trend reports, and production-release documentation.

Audit & Inspection Readiness

A documented pre-operational inspection program can help demonstrate how production readiness is evaluated during:

  • HACCP certification audits
  • Regulatory inspections
  • Customer audits
  • GFSI certification audits
  • Sanitation investigations
  • Environmental monitoring reviews
  • Internal food safety audits

Complete HACCP Support

CIG supports organizations throughout the HACCP lifecycle, including:

  • HACCP Readiness Assessment
  • HACCP Plan Development
  • Hazard Analysis
  • Prerequisite Programs
  • Pre-Operational Inspection Programs
  • Sanitation Programs
  • Environmental Monitoring
  • Allergen Management
  • Hygienic Zoning
  • Preventive Maintenance
  • Foreign Material Controls
  • Calibration & Measurement Controls
  • Product Hold & Release Controls
  • Validation
  • Verification
  • Corrective Actions
  • HACCP Reassessment
  • Audit Readiness
  • Ongoing Compliance Management

Establish a Food Safety Checkpoint Before Every Production Start

The window between sanitation and startup.

The period between sanitation completion and production startup is one of the most important opportunities to identify and correct food safety conditions before product is exposed.

CIG helps organizations establish a structured pre-operational system for inspection, sanitation verification, equipment readiness, deficiency correction, reinspection, documentation, and production release.

Start Your HACCP Pre-Operational Inspection Program

Whether you are developing pre-operational inspections for the first time, improving existing sanitation verification, addressing repeated deficiencies, strengthening production-release controls, or preparing for an audit, CIG can help. Build a pre-operational inspection program designed for production readiness, sanitation verification, early hazard identification, controlled release, and HACCP integrity.